Can I continue a PlumePack process which failed or did not finish ?
Yes ! From PlumePack 3.1, we implemented the "Reload" feature. Go to the "Finished Queue" and click on the reload button of the task you want to reload. A new task will be created in the "Pending Queue" from that past task. You should also see a dropdown with choices of where you want to restart the task.
Note that reloading a task after "Project Analysis" (so at the "Trim" checkpoint of after), will not process the successful trim/transcode/copy actions a new time.